Progess...Slow, but Steady
Progress is finally being made on the exterior of the home. The back porch now has a roof and the front porch will have a floor and a roof by the end of this week. How exciting! The boys and I have been visiting the house several times a day to make sure everything is going like it should. We are making ourselves at home as much as possible.
Wednesday, December 15, 2010
Demolition
Demolition has finally begun! We are having some of the roof taken off and repaired due to water damage and poor construction. I can't wait to see how different the house is going to look after all the overhangs are complete. We have decided on a tin roof too. How fun!
Wednesday, November 17, 2010
Trees are Gone!
The trees are gone! The house looks so different now and we are ready for work to begin...We went ahead and moved the boys fort to the backyard. I'm sure it will be put to good use. Still getting together estimates for paint, cabinets, flooring, etc. So many choices! I am envisioning heart pine 6" planks flooring and butterscotch (distressed look) cabinets.
Look at the size of that stump! Now that was a huge old oak tree.
This tree just had some limbs trimmed off. They were completely across the roof and were about to grow into the chimney.
Look at the size of that stump! Now that was a huge old oak tree.
This tree just had some limbs trimmed off. They were completely across the roof and were about to grow into the chimney.
Wednesday, November 3, 2010
Monday, November 1, 2010
Upcoming Closing
Our closing is scheduled for November 19th and we are really getting excited. The bank (the house is a lender owned property) just put up a door to the outside of the garage (with a lock) and nailed up boards covering the front door opening. The agent for the bank told us we can go ahead and get ourselves keys made so we can come and go as we wish. How exciting! We met with our bank last week and the paperwork is now underway. In just 2 short weeks, our finishing job will begin!
Thursday, October 28, 2010
Welcome to Project 1852
approximately 3500 sq/ft. One half acre lot. Hardy plank exterior. Inspection shows home is structurally sound.
View of beautiful houses across street. Check out those huge old oak trees!
View of front portion of home from near the back porch. Notice the tarp for the front door and the interior columns.
Front porch view with no flooring yet just a plank to enter house. Visible water damage on front rafters.